Method Statement [top] | Tower Crane Dismantling
Tower Crane Dismantling Method Statement is a high-level safety document that details the specific sequence, equipment, and precautions required to safely decommission a tower crane. Because dismantling is a high-risk operation involving heavy loads at height, strict adherence to a pre-approved sequence is critical to maintain structural balance. 1. Pre-Dismantling Preparation
A professional method statement should include the following sections to ensure compliance and safety: Scope of Work tower crane dismantling method statement
- The crane has completed all lifting duties.
- The surrounding area (drop zone) has been cleared of non-essential personnel.
- Ground conditions are stable for mobile crane positioning.
- Weather forecast is acceptable (wind speed < 20 mph / 9 m/s sustained).
Environmental Considerations
- Perform a final operational check of the tower crane. All slewing, hoisting, and luffing functions must work perfectly for the initial rigging.
- Inspect all wire ropes, shackles, and anchor bolts for corrosion or wear.
Assist Crane:
A mobile crane with sufficient capacity and reach (e.g., a 250-ton or 500-ton crane). Hand Tools: Impact wrenches, drift pins, and sledgehammers. Tower Crane Dismantling Method Statement is a high-level
Phase 6: Base and Foundation Removal
- Do not remove all counterweights at once.
- Remove counterweights in the reverse order of installation, using the mobile crane.
- Critical: Maintain stability to prevent the crane from tipping backward.