Creep and Relaxation Modeling

  1. New Project → Name “Main St Rebuild”
  2. Add Poles → Pole 1 (40ft wood), Pole 2 (40ft wood), Span = 250ft
  3. Add Conductor → 477 ACSR, 25% RTS initial tension
  4. Run Sag → Accept default temps
  5. Add Attachments → 50kVA xfmr @ 20ft on Pole 1
  6. Load Cases → NESC Heavy + Extreme Wind (90mph)
  7. Analyze → Review pole utilizations (<100% passes)
  8. Generate Report → PDF stringing table + clearance diagram

2. Conductor Sag & Tension (Stringing Charts)