MEP Work Progress Report — Sample
- Overall progress: 50%
- Completed: main switchboard installation; lighting conduits and power backboxes installed on Levels 1–4.
- In progress: cable tray installation in service corridors (70%); distribution panel wiring (30%).
- Issues: procurement of specific NEMA connectors delayed — expects 3-day lead recovery.
Before we dive into the sample, let’s review the 8 critical sections every MEP report must contain:
- Overall progress: 35%
- Completed: wet risers installed to Level 4; fire pump room construction complete.
- In progress: sprinkler branch installation Level 1–3 (50%).
- Issues: sprinkler heads awaiting final selection confirmation from client.